Replacing window frames in the protection zone of a listed building is exempt if the new ones improve energy efficiency, keep the same geometry and look the same from outside. For a listed building itself it is not exempt.

Ask for a free check

Answer
Exempt in the protection zone if the conditions are met
Conditions
Better energy efficiency, same geometry and proportions, outside finish identical to the original
Listed building
Not exempt for the listed building itself or listed groups and sites (art 6-A(2))
Before you start
Tell the council at least 5 days before work begins, even for exempt work (art 80-A).
Council rules
Your council can add detail in its own building regulation where the law lets it, so ask before you start.
Legal basis
RJUE art 6-A(1)(j) and 6-A(2), RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026
Sources
data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
Checked
2026-11-05

More: How the permit rules work

Free check

Send us your question about a planned work. We will answer it by email, based on the national rules and the sources shown on the page. It is free.