Interior work that touches the structure is exempt only with a stability project and a responsibility statement from a qualified technician saying it improves or does not harm stability. File them with the start-of-works notice.
- Answer
- Exempt from licence only with a stability project and signed statement
- Technician statement
- Says the works, taken as a whole, improve or do not harm the stability of the building (art 6(1)(b)(ii))
- Seismic reinforcement
- A seismic reinforcement project is also needed where the law requires it
- Filing
- Deposited with the notice of start of works (art 80-A)
- Condition
- Nothing changes on the outside of the building
- Council rules
- Your council can add detail in its own building regulation where the law lets it, so ask before you start.
- Legal basis
- RJUE art 6(1)(b) and 80-A, RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026
- Sources
- data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
- Checked