Levelling or earthworks: do you need a permit in Portugal?
Earthworks that destroy plant cover, change the natural relief or topsoil, or fell large trees, for non-farming purposes, are land remodelling (remodelação de terrenos) and need a licence, unless a plan or subdivision already sets the works.
- Answer
- Licence
- What counts
- Destroying plant cover, changing the natural relief or topsoil, or felling tall or clustered trees, for non-farming purposes (art 2(m))
- Prior communication instead
- Only in an area covered by a subdivision, detail plan or execution unit that already defines the works (art 4(4)(c))
- Small garden works
- Small arrangement works that do not affect public land are exempt (art 6-A(1)(d))
- Council rules
- Your council can add detail in its own building regulation where the law lets it, so ask before you start.
- Legal basis
- RJUE art 2(m), 4(2)(b) and 4(4)(c), RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026