Home energy storage units are exempt under the same limits as solar panels, as long as the storage unit is hidden from view. Outside those limits the general rule is a licence.

Ask for a free check

Answer
Exempt from licence and prior communication
Limit
Not beyond the roof area of the building and not more than 1 m above its height
Condition
The storage unit must be concealed
Before you start
Tell the council at least 5 days before work begins, even for exempt work (art 80-A).
Heritage exception
Minor-works exemptions do not apply to listed buildings, buildings in the protection zone of a listed building (window frames excepted), or buildings inside listed groups or sites (art 6-A(2)).
Council rules
Your council can add detail in its own building regulation where the law lets it, so ask before you start.
Legal basis
RJUE art 6-A(1)(g), RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026
Sources
data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
Checked
2026-11-05