Altering a listed building: do you need a permit in Portugal?
Altering, extending, rebuilding or demolishing a listed building, or one being listed, needs a licence. The minor-works exemptions do not apply to it.
- Answer
- Licence
- Prior communication
- Only after a favourable prior information (informação prévia) that covers all the required elements (art 4(4)(l))
- Minor works
- Excluded for listed buildings of national, public or municipal interest and for listed groups or sites (art 6-A(2))
- Council rules
- Your council can add detail in its own building regulation where the law lets it, so ask before you start.
- Legal basis
- RJUE art 4(2)(d), 4(4)(l) and 6-A(2), RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026
- Sources
- data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
- Checked
- 2026-11-05
Free check
Send us your question about a planned work. We will answer it by email, based on the national rules and the sources shown on the page. It is free.