Adding a storey: do you need a permit in Portugal?
Adding a storey is an extension of height and volume (ampliação) and needs a licence. Prior communication applies only where a plan or subdivision sets the details, or in a consolidated urban zone under the height rule.
- Answer
- Licence
- Prior communication instead
- Prior communication replaces the licence only where a detail plan, execution unit or subdivision already sets the details, or in a consolidated urban zone with no cessions and a height no taller than the most common facade height on that stretch of street.
- Extension means
- Works that increase the facade height or the height or volume of a building (art 2(e))
- Council rules
- Your council can add detail in its own building regulation where the law lets it, so ask before you start.
- Legal basis
- RJUE art 2(e), 4(2)(c) and 4(4)(d) and (e), RJUE (Decreto-Lei 555/99) as republished in the Annex of Decreto-Lei 108/2026
- Sources
- data.dre.pt/eli/dec-lei/108/2026/05/29/p/dre/pt/pdf
- Checked
- 2026-11-05
Free check